For architects and designers: electrical, automation and network guidelines at the design stage

The cheapest moment to plan installations is the design. Based on the floor plans we prepare guidelines: location and size of the distribution board, cable routes, power for external shading, network and airtight installation penetrations.

  • „The client wants automation but has not chosen a system yet.”
  • „Blinds and shading have to be planned together with the facade.”
  • „In a passive house, installations must not penetrate the airtight layer.”

Three layers

What do we combine into one system?

We design the electrical installation, automation and network together, so they work as one system with one party responsible.

Electrical

  • Location and size of the distribution board
  • Cable routes and boxes
  • Power supply for external shading

Automation and security

  • Placement of sensors and panels
  • Shading against overheating
  • Cabling for Loxone or Ampio

IT

  • RACK cabinet and network points
  • Placement of Wi-Fi access points

Construction stages

Ideally before the detailed design is made

It costs least at the design or shell stage. The later it gets, the more changes to a wired installation require chasing walls; wireless systems are the exception.

Construction stages, scope of work and cost of changes
StageWhat we do thenCost of changes
DesignGuidelines for the design: distribution board, routes, external shadinglowest
Open shellConduits and penetrations without thermal bridges, Power supply for blind boxeslow
Closed shell (windows installed)Blind and shading drives, Window contacts, Airtight installation penetrationslow
Before plasteringCabling, Measurements, Presence at the airtightness testmedium
After plasteringWireless systems (Loxone, Ampio, Somfy), Minimal wall chasinghigherapplies to wired installations; with a wireless system the cost does not increase
Renovation / retrofitAssessment of the existing installation and distribution board, Wireless systems where there are no cableshigherapplies to wired installations; with a wireless system the cost does not increase

Who does the work

What do partners do?

Some work requires other qualifications. For each of them we state clearly whether we coordinate it or recommend a partner.

  • We coordinate – done by a partner

    Carried out by: partner carrying out airtightness tests

    Airtightness test (blower door)

    After the airtight layer and before finishing; we are on site and seal our own penetrations.

FAQ

Frequently asked questions

At which construction stage is it best to contact you?

At the design or shell stage, before plastering. At that point we plan the distribution board and routes based on the floor plan, and changes cost least. In renovations we use wireless systems.